Organizational Rule No. (1) for the year
1993
Organization of the relationship between
General
Supplies
Department on one side, and the
ministries,
government departments and institutions
on the other side
.
In view of
the several needs and requirements of
the ministries and the government
departments, of various supplies to
improve work performance and guarantee
its continuity, and since the most
important duties of General Supplies
Department are to purchase such supplies
on behalf of the ministries, departments
and public institutions, according to
Supplies Act and the instructions issued
accordingly, and in order to enable this
department to implement the functions
assigned to it on time, ministries,
departments and public institutions
should abide by the following procedures
:-
1) Determining and confining the
allocations designated for purchasing
purposes, whether from the budgets or
from the deposits or projects
allocations, or any other source to be
implemented through General Supplies
Department, following the approval of
the general budget or the budgets of the
independent departments.
2) Determining all the allocations
to be implemented by General Supplies
Department, and categorizing these
allocations according to the articles
and items of the budget of such
department or other intermediate
accounts (deposits, projects and grants…
etc.).
3)
Listing of supplies to be purchased and
categorizing them according to their
kinds, and including similar supplies in
one purchasing request.
4)
Preparing general, accurate, clear, and
complete specifications for the required
supplies, without referring to trademark
brand, or trade number or any
information that makes these
specifications limited to one source,
and they can ask for General Supplies
Department assistance in the laying down
of such specifications.
5)
Verification of the actual need for
purchasing and dispatching purchasing
requests on the forms prepared for this
purpose, to General Supplies Department,
within the first four months of the
fiscal year, and every purchasing
request should be supported by the
followings :-
A-A duly
certified financial obligation bond with
the complete estimated value, or the
approval of the Prime Minister on
purchasing, or the approval of the
Minister of Finance / general budget as
the case requires.
B-General
and clear specifications for the
required supplies, including the
following: -
1-A brief
technical report stating that the
specifications provided are general and
valid for a tender's invitation, and in
case the supplies can be obtained from
one source only, this should be written
explicitly on the purchasing request
together with the supplier's address
precisely and clearly, and the name of
the local agent.
2-Approving
such specifications in writing by the
under-secretary of the beneficiary
department or any person he authorizes.
C-Any
approvals/exceptions from the Cabinet
announcements, or other official
parties, necessary to accomplish the
purchasing process.
D-Nomination of technicians to
participate in the technical study when
necessary.
6)
Dispatching the purchasing requests and
their supporting documents mentioned in
item (5), with official letter / letters
to General Supplies Department, and it
is preferable to deliver them personally
against signature as a notification of
receiving.
7)
General Supplies Department should
review the purchasing request and its
supporting documents, and return the
purchasing request to its source, in
case its supporting documents were
incomplete, in a manner that the
purchasing process can not be initiated.
8)
General Supplies Department should
categorize the similar purchasing
requests and invite for them in one
tender.
9) Not
to purchase any supplies that General
Supplies Department announces its
intention to purchase them in periodical
/ common tenders, regardless of their
value, whereas coordination should be
made between General Supplies Department
and the other ministries and departments
to obtain them, whether free or for
price as the case requires.
10) Cooperation with General Supplies
Department by facilitating the task of
the technicians and experts nominated or
asked to be nominated by the director
general of General Supplies Department,
and giving them sufficient time to
accomplish the functions assigned to
them.
11)
Following up the awarding decisions and
the purchasing orders issued by General
Supplies Department, and providing it
with the duly documents which prove the
implementation of the decision and
purchasing order (receiving voucher,
entry voucher and any letter stating
that the service had been implemented)
in order to complete the contractor’s
obligations and close the tender’s file.
12) Requesting General Supplies
Department to apply, without delay, the
provisions of Supplies Act and the
awarding decision against the slack
contractor.
13)
Following up the awarding decisions and
purchasing orders in which the delivery
duration will be in the next year, to
rebalance the allocations necessary
thereto.
14)
Dispatching the late purchasing requests
before the beginning of October every
year, and not to accept any purchasing
request arrives after this date, except
for emergency and justified cases,
approved by the director general of
General Supplies Department, with the
exception of the purchasing on the
account of the next year, following
obtaining the required approvals
according to the Act.
15) Rejecting any supplies
violating the specifications and
conditions of the awarding decision, and
requesting the contractor to withdraw
them within (48) hours, and deliver the
supplies consistent with the
specifications, and in the cases in
which the requesting department deems
that receiving such supplies is to its
interest, then it should submit its
submission to General Supplies
Department to accept such supplies,
according to the central tenders
committee's decision.
16) The
contractors due amounts should be paid
according to the contents of the
awarding decision and the purchasing
order.
17) Bid bonds, performance bonds,
maintenance bonds, and
mal-manufacturing guarantees should be
submitted in the name of General
Supplies Department and kept therein.
18) The purchasing orders that
related to the annual periodical
contracts should be sent to General
Supplies Department at least three
months before the contract expiry date.
19)
Every department should appoint a
liaison officer in General Supplies
Department, to follow up the
accomplishment of purchasing processes
relating thereto in G.S.D., and complete
any requirements for work accomplishment
without delay.
This rule
should be acted upon from 1/3/1993.